A major Teesside-based project which will incinerate household waste from across the North-East has fallen behind schedule and will not now be fully operational until at least 2029, it has emerged.
The £300m Tees Valley Energy Recovery Facility (TV ERF), which is being overseen by a partnership of several councils in the region and is due to be built on the Teesworks complex on land west of Tees Dock Road, Grangetown, faced uncertainty around what date it could be connected to the National Grid due to a current lack of transmission network capacity.
As a result the evaluation of tenders submitted by two shortlisted potential operators, Viridor and Green Recovery Projects Limited was stopped.
In a letter to Energy Secretary Ed Miliband Denise McGuckin, the managing director of Hartlepool Council who chairs the project board, said the procurement process had now restarted after two viable connection offers were received earlier this year, with a corresponding Q&A published online acknowledging the “knock on impact”.
Providing an update, she said: “On current timescales, optimised final tenders are expected to be received by the end of this year and a preferred tenderer appointed in 2025 with the facility entering full operation from 2029.”
Construction, testing and commissioning of the facility, which is predicted to generate enough electricity to power the equivalent of 60,000 homes, is expected to take four years.
Earlier stages of the project had seen April 2026 identified as a potential start date.
Six of the seven councils involved are due to see their existing residual waste – rubbish left over after household recycling – treatment commercial arrangements expire in 2026.
A spokesman said various short-term market options were now being considered in the interim, the bidders having also been requested to propose and include solutions from 2028.
In her letter Mrs McGuckin said the facility – which will take about 450,000 tonnes of waste each year produced by 1.5m people living in Darlington, Durham, Hartlepool, Middlesbrough, Newcastle, Redcar and Cleveland and Stockton – was “vital” and would ensure local authorities could fulfil their statutory duty, while offering environmental and economic benefits.
She said: “By procuring a new facility and specifying the location of the project, the councils are able to overcome a local monopoly situation, guarantee best value for money and both remediate and economically regenerate a contaminated brownfield site left vacant by the closure of British Steel.”
Mrs McGuckin referenced how the project was unsuccessful last year in efforts to secure Carbon Capture and Storage (CCS) funding from the Department for Energy Security and Net Zero, which would have allowed it to be developed with these elements from the outset.
She said: “However, we believe the TV ERF project remains well placed to apply again in future phases and could play a valuable role in the pursuit of national net-zero targets. “The TV ERF has been designed to be ‘carbon-capture ready’, thereby ensuring that sufficient space remains on site to allow the retrofitting of carbon-capture infrastructure to be installed in future, should an opportunity arise.”
She said the amount of greenhouse gases produced would be reduced compared to sending waste to landfill – a frequent argument put forward by supporters of the project.
As part of the tender specification the bidders have been required to demonstrate how they will reduce carbon dioxide output year-on-year through operational efficiencies and will be given targets.
‘Complementary to efforts to recycle more’ Mrs McGuckin said the facility “remains complementary to ongoing efforts to recycle more”. She added: “The project exists, and is permitted, within a mature and robust regulatory framework covering planning, environmental protection and public health.
“The TV ERF remains the most secure, reliable, safe and affordable solution for making the most of the waste left over after recycling in the region.”
The successful bidder will design, finance, build and operate the plant, recouping their upfront costs through a service fee paid by the councils and energy receipts from electricity offtakes with its ownership reverting to the partner authorities once a contract which could extend up to 40 years expires.
Full planning consent was given by Redcar and Cleveland Council in July last year following applications submitted by Viridor and Green Recovery Projects Ltd.
At the time Paul Foster, of the campaign group Stop Incineration North East, said Teesside already had four working incinerators in the area with several more in the pipeline.
He said incinerator bottom ash produced, which will be transported off the intended site, had an “insidious toxic nature”, while the group also said flue emissions which would be released into the air contained nitrous oxides, ultra fine particles and dioxins, for which there was no safe level.
The Q&A said mature, proven and reliable technology would be used to treat flue gases, resulting in “only a small, if detectable, contribution to local concentrations of pollutants such that any impact on health from reduced air quality is negligible”.
Last month Councillor Tristan Learoyd, who objected to the scheme while chairing Redcar and Cleveland Council’s regulatory committee, wrote to Energy Secretary Mr Miliband to ask him to stop this “planet and health destroying madness”.
He said the project “dumps an incinerator on one of the most deprived areas in Europe” and was an incentive to “burn and not recycle”.
The TV ERF project will create several hundred jobs during the construction period and up to 50 permanent positions once operational.
Most read:
- Tributes paid to man who died after motorcycle crashed into County Durham road sign
-
How a 187-house County Durham estate will look once built as work starts
-
All the North East locations you can go by train for as low as £3 until November
Get more from The Northern Echo with a digital subscription. Get access for 6 months for just £6, or get 50% off an annual subscription with our latest offer. Click here.
The Q&A published on behalf of the project partners referenced moratoriums on so-called Energy from Waste plants imposed by devolved administrations in Wales and Scotland.
It said the project was “not a speculative commercial project and has been carefully designed to serve known and anticipated regional need within a range of future policy and performance scenarios over its operational lifetime”.
The waste due to be supplied was in full control of the partner authorities, which had a legal duty for its safe treatment in perpetuity, and it was not anticipated the facility would be affected by any future restrictions.
Comments: Our rules
We want our comments to be a lively and valuable part of our community - a place where readers can debate and engage with the most important local issues. The ability to comment on our stories is a privilege, not a right, however, and that privilege may be withdrawn if it is abused or misused.
Please report any comments that break our rules.
Read the rules hereLast Updated:
Report this comment Cancel