A footbridge in Durham City has been earmarked for demolition after detailed investigations determined its structural defects are beyond repair.

Leazes Footbridge was closed last July after a routine inspection by Durham County Council officers identified structural issues that required a more detailed examination.

Since then, the bridge, which crosses the A690 and provides pedestrian access from Claypath to the city centre and the riverside, has been the subject of multiple surveys by a specialist contractor.

Investigations have confirmed integral components, including the joints to the underside of the bridge, are failing and the structure is no longer safe to bear the weight of pedestrians.  

The nature of the defects mean they cannot be repaired, and while there is no immediate risk of the footbridge collapsing, this could change if the bridge remains in position, exposed to the elements.

As a result, Durham County Council has earmarked the bridge for demolition before the summer.

The demolition will take approximately four weeks, with the central span removed overnight under a full road closure.

The signed diversion for pedestrians and cyclists will remain in place, and pedestrians are advised against crossing the A690 at any other location.

Most read

 

Get more from The Northern Echo and start 2024 informed with 50 per cent off an annual subscription or enjoy 3 months for just £3. Click here 

Paul Anderson, strategic highways manager at Durham County Council, said: “We understand Leazes Footbridge was well-used, and the decision to demolish the structure is not one that has been taken lightly.

"Following its closure last summer, experts have gained an in-depth understanding of the structural integrity of the footbridge and have confirmed the defects are irreparable.

“Public safety is our main priority and, as such, we are now making arrangements for the demolition of the footbridge. We will provide further information about the programme of works in due course, and I would like to thank the public for their ongoing patience.”

Durham County Council will be reviewing options following the demolition of the bridge.

Plans include introducing a pedestrian crossing at the existing traffic lights located at the top of Leazes Road at Gilesgate Roundabout.